New Builds · Birdlip, Gloucestershire
Project overview
Work is well under way on a new stone-faced building in the Cotswold village of Birdlip. From setting out and excavating the foundations to raising the external walls, these photos follow the build as it happens. The stone facing has been chosen to sit comfortably alongside the village's Cotswold stone cottages. We'll keep adding photos as the project progresses.
Build progress so far
Setting out and foundations
The site was set out and the foundation trenches excavated.
Substructure
With the foundations complete, the blockwork walls were built up from them.
Waterproofing
The blockwork was wrapped in a dimpled waterproofing membrane.
Walls going up
The internal blockwork walls are in, and the external walls are rising in stone with the window and door openings formed.
Photography